Home › Curriculum › Implementation Consulting › User acceptance testing and sign-off
Testing, UAT, training and go-live · 12 min · methodUser acceptance testing and sign-off
Planning UAT with the project manager, preparing scenarios, guiding users, managing findings and getting formal sign-off.
In this lesson
- The UAT plan
- Running UAT and managing findings
- Formal sign-off
Key points
- UAT plan: scope, people, environment, schedule, entry/exit criteria
- Users test real-looking scenarios; guide first runs
- One findings log: severity, class, owner, status, traceability
- Written sign-off with known issues listed
Real-world example
A client's finance director refused to sign UAT because of '50 open issues'. The log, classified, showed 4 defects, 6 configuration items, 3 data items, 31 training questions and 6 change requests. Fixing the 13 real items and running a training session got sign-off in three days, with the change requests scheduled for phase 2.
Questions and answers
Why list accepted known issues in sign-off?
So everyone knows what goes live with limitations and the plan to fix them.
Who owns the UAT plan?
The project manager, supported by the consultant.