Testing, UAT, training and go-live · 16 min · method + 19–20Go-live cutover and hypercare
Go-live readiness, the cutover plan, final validation, the first days in production and the hand-over to support.
In this lesson
- Readiness checklist
- Cutover runbook and production validation
- Hypercare and transition to support
Key points
- Readiness: UAT, training, data, rights, integrations, mail, backups, rota, rollback
- Hour-by-hour cutover runbook, rehearsed on staging
- Validate each critical flow in production, then reverse test data
- Hypercare: daily stand-ups, monitoring, escalation with evidence, formal hand-over
Real-world example
On a Monday go-live, invoices failed to email. The hypercare checklist had 'outgoing mail server configured in production' ticked, but the SMTP password was the staging one. Because log monitoring was on the hypercare rota, the consultant saw the authentication errors within 20 minutes, fixed the server and re-sent the queue before customers noticed.
Questions and answers
Name three things to monitor in hypercare.
Logs/errors, scheduled actions, email queue, performance (also integration logs).
What ends hypercare?
A formal transition to support and a lessons-learned review.